Motorists in Isolo and surrounding areas of Lagos should prepare for traffic disruptions as the Oke-Afa Bridge undergoes rehabilitation for three weeks.
The Lagos State Government announced that the bridge will be temporarily closed to vehicular traffic from Friday, 28 August, to Friday, 18 September 2026. Works will be carried out in two phases to minimise disruption. The first phase, covering the outbound Isolo-to-Ejigbo axis, runs from 28 August to 11 September. The second phase, affecting the inbound Ejigbo-to-Isolo section, takes place from 12 to 18 September.
During the first phase, vehicles travelling from Isolo towards Ejigbo will be diverted onto the Isolo-bound carriageway from Pako Roundabout, where traffic will move in both directions before rejoining the main road at Mobil Filling Station. Motorists from Ejigbo will share the carriageway in the opposite direction until the roundabout.
In the second phase the arrangement will reverse, with diversions starting from Mobil Filling Station for those heading towards Isolo.
The rehabilitation is being handled by the Federal Ministry of Works through the Office of the Federal Controller in Lagos, with Strabic Construction Limited as contractor. The Lagos State Traffic Management Authority will be on hand to guide motorists and ease congestion. Officials have urged cooperation and patience during the works, which aim to improve the safety and longevity of the busy link between Isolo, Ejigbo and nearby communities.